Page 13 of 16
11. The IRIS Touch will now perform tests over the Ethernet path to confirm
polling and alarm are being received by the monitoring centre.
If you receive a failed message you will be indicated on the screen some
reasons for this, please contact Chiron Technical Support if further assistance
is needed.
Note: If not using GPRS as a communication path then please jump to
line 12
12. The IRIS Touch will now perform a test poll and alarm over the GPRS network.
Please confirm both tests pass successfully.
If you receive a failed message you will be indicated on the screen some
reasons for this, please contact the GPRS SIM provider if further assistance is
needed.
13. “Test Completed” Click “Finish”.
Installation is now completed successfully.
Please click the “back” button to return to the welcome screen. The message
“Status - System OK” is displayed on the welcome screen and the LED
Indicator on the PCB is on steady.
You are now ready to do you site commissioning of alarms and any
download testing.